Work on 506 is now largely in the hands of the MHR engineering team. With the running fleet to be maintained as well, work may sometimes appear sporadic but the guys are pushing on with the overhaul as best they can. Certain jobs have been done/are to be done by our own guys but to start splitting out who’s done what seems a bit daft … we’re all working together as one team to try and ensure 506 returns to traffic later this year. So, to summarise the work done by all parties since my last post:
- New brake hangers are now riveted to the frames
- New piston and valve cover studs have been made
- Brake rigging has been refurbished; crossbars and pull rods
- Brake
weighshaft has been machined - Mating faces for the blastpipe and main steam pipes have been faced up
- Blastpipe infill pieces have been finished and fitted
- 4
axleboxes have been machined and white-metalled - Leading and centre driving wheelsets are in
- 1 new axle box has been completed, the other is machined and awaiting white-metalling. The axle boxes have proved a bit of a saga. Some of you may recall that 2 of our original boxes were u/s so the plan was to replace these with a pair of new castings the Society had made some 15 years ago. Unfortunately, once the MHR guys started to machine them, it because
clear they had more air holes thana Swiss cheese . There was no option but to scrap these and start again with brand new castings. As you can probably imagine, we were all hugely frustrated by this backward step, not only because of the time needed to obtain 2 more castings but also because after such a long period of time we have no recourse to the foundry for the first ones. - The front bogie is now completely refurbished and awaiting final assembly
- Wear in the bores on the coupling rods has been built up with weld
- The boiler casing is undergoing repairs as necessary
- A special tap has been made to re-cut the steam pipe studs in the cylinder blocks
- Whilst all this has been going on, the frames and cab sides have been prepped and painted; it’s all looking pretty good!
- Planning ahead, the tender has been moved into the yard for finishing. For those interested in the detail, this is the new tender tank (on the chassis rescued from Eastleigh works) built to ultimately run with 499; 506’s own tender is u/s with thin tank sides and a question mark over the frames. Ultimately we plan to build another new tender using frames we have from 30825 – just need a few more hours in the day!
Whilst the reaming has been going on, a couple of us decided to grind off a few firebox stay heads on boiler 799 as a bit of an ‘in-fill’ job. In fact, things have gone so well that the boiler has become a project, at least 1 year ahead of schedule. Most of the stays below the grate will have to be removed. The outside heads of these have been ground flush to the steel plate and pilot drilled to a diameter of 8mm. Inside the firebox the stays marked for removal have been ground flush with the copper plate. This grinding requires much more care than the outside – nick the steel and a simple weld repair sorts the problem; nick the copper and it’s a whole different issue!! Those who have been to Ropley lately may have noticed that the smokebox rivets have been removed from boiler 451 (nearest the yard). To allay any confusion, boiler 799 IS the one chosen for 499 on the basis of economics – 451 requires a new copper crown. However, because it is sited nearest the yard and the easiest to work on, we are removing the latter’s smokebox to enable us to use the barrel as a template for a new smokebox. I have seen a comment on one of the chat rooms about the type of smokebox door we intend to use. Clearly we would love to have a proper Urie style door made, but because of the shape it is currently looking cost-prohibitive. The ULS doesn’t give up easily though, we will keep looking for a way round this and I will keep everyone informed of progress. In the meantime, should any of you win the lottery please contact the Urie Loco Society …..!!
Whilst the reaming has been going on, a couple of us decided to grind off a few firebox stay heads on boiler 799 as a bit of an ‘in-fill’ job. In fact, things have gone so well that the boiler has become a project, at least 1 year ahead of schedule. Most of the stays below the grate will have to be removed. The outside heads of these have been ground flush to the steel plate and pilot drilled to a diameter of 8mm. Inside the
Back to the ‘here and now’, we will be holding our 3rd annual open day on 30th June this year. Yes, it is all about fundraising to keep our projects on track, but it is also a day when the engineering team stays clean and we make ourselves available to meet members and visitors and answer any questions they may have. If you can spare a few hours why not come along for a chat and see the work we do close up. You will have access to both locos; 506 is currently a 4-4-0 but is likely to be an 0-6-0 come the 30th! The rear drivers are ready to go in soon, the accommodation bogie will be taken out but the refurbished bogie won’t go in immediately … we need access to the cylinder bolt nuts to do a final check for tightness (in other words we need to get in there with a large spanner and hammer!). Return to a 4-6-0 is likely to be during July. Back to the 30th, you’ll be able to browse the books for sale in our sales cabin, see our photographic record of the work done since 2011 and watch archive footage of 506. We will be showing some of the components we have made and there may also be one or two surprises for you to see this year. Maybe you could consider taking our a membership or signing up for the 499 Appeal; remember, this is a unique project to return the loco to her 1920 as-built condition and you can be part of that. Also in attendance on the day will be our President, Bob Urie – grandson of the great man – and our Honorary Patron, Mark Collins, radio presenter on Wave 105 and renowned railway enthusiast; both will be delighted to meet you.